Segment 7
|
Where:
South of I-85 near Archdale to US 220, near Randleman,
Randolph County
Length: 13 Miles
Needed: Finish Constructing New Freeway
Current Highway signed:
Estimated Completion Date:
November 2010 for First Section,
Late 2012 for remaining section
|
I-74 will continue on a new freeway from
south of I-85 near current Exit 113 in Archdale to US 220 (I-73) near
Sophia, north of Asheboro, connecting to US 220 south of the current
US 311 interchange along a path approximated
by the red dashed line in the map above. When this specific
route was chosen in 1997 it disappointed many citizens
and government officials in the area since the route cuts
a 1000 foot wide path directly through the city of Sophia
before meeting US 220. Despite many objections, NCDOT chose
this route, designated Corridor C, rather than the Corridor AA
route prefered by the public at June 1997 hearings, because it
cost $7 million less, avoided a complicated interchange with US
220 (I-73), and would send the least amount of pollution to the
future Randleman Reservoir, preventing potential environmental
problems. (1, 2) The project is listed in the 2009-2015 NCDOT
STIP as Number R-2606. (3) Right-of-Way acquisition started on
the western part of the route in 2003, with a total cost projected
at $17.5 million. Construction on the first section, $28.5
million of the total construction cost estimated
at $177 million, started on May 29, 2007 (see below). (4) This section
will feature an interchange at Cedar Square Road (listed in contract
documents as Exit 79) which will be the temporary end of I-74
while the remaining segment is still under construction. US
311 will be temporarily routed along Cedar Square road back to its
current alignment. The US 311 route from there westward (northward)
was to be redesignated US 311 Business, but in the Spring of 2009 High
Point officials asked that NCDOT remove the designation where it existed
in High Point, and thus it no longer will run along its proposed route to
the south (see photo in Section 6). (5) The next segment totalling 7.9
miles is being built as a design-build project. This was let in August
2008 with Barnhill Contracting being the winning bidder with a cost
of $99.7 million. Construction started in September 2008 and is now listed
as about 20% complete. (4) There will be an additional exit where the
freeway crosses the current US 311 in Sophia along with the interchange
with US 220 (I-73) at the end of this segment. (6)
This
segment had been dubbed the "Missing Link" by
the I-74 Piedmont Corridor Group (PCG), an organization
of business people, transportation officials,
and others lobbying to complete I-74. They created the
term in 2003 to call attention to what they saw as NCDOT's too
drawn-out segmented plan to complete this portion of the
highway, long after many other sections of I-74 were then scheduled
to be built. The PGC hoped to put enough pressure on NCDOT
to move up its construction timetable for the entire section
to match work starting on Segment 6 to the west.
Starting both projects at once, supporters said,
would be more efficient. (7) This effort
seems to have eventually paid off. While start of construction
was delayed from October 2006 to May 2007, work on
the first part, 5.3 miles from south of I-85 near Archdale
to north of Spencer Road (SR 1929) in Glenola,(8) will began
at the same time as work was started on the remaining section
of Segment 6. (9)
Also, whereas earlier
plans called for the proposed letting for the next part
of the highway, from Spencer Road to US 220 in Sophia, not to
occur until after 2012 and be done in two parts, the final part
not to begin a couple years after that (10), the project instead
got most of the funds borrowed under the Garvee Bond Program
to expedite the work that started in the latter half of 2008.
These borrowed funds ($112 million) will then be paid back out
of the highway fund accounts through 2019. (3) The first section
should be completed by November 2010, or earlier, and the second segment
may be finished by Fall 2012.
A summary
of construction on the first section from west to east, with photos below,
through early April 2010 (11):
The I-85/I-74 Interchange
Flyover Ramp:
The flyover ramp appears
to be complete in this photo from April 2010, much as it had been earlier
in the year. (4/11/10)
Appearance of the
Flyover Ramp in January 2010. Note the lack still of a tie in from
the ramp on the left. Guardrails and asphalt need to be applied to complete
the link to the previous bridge, this was still the case in April. An
asphalt layer has been completed from the right side of the bridge to
I-85. (1/14/10)
The ramp
as it appeared in November 2009, note still the need to put in concrete
walls along the bridge structure, the container units are on the future
on-ramp to I-74 East. (11/8/09)
A closeup look at the
transition between the flyover ramp and bridge structure, showing
there still remains work to do to finish the bridge and tie it to
the approaching roadway. (4/11/10)
A similar
closeup from November 2009, showing there has been some progress, but
there remains work to do to finish the bridge and tie it to the approaching
roadway. (11/8/09)
View
of progress on Flyover Ramp from I-74 East to I-85 North two months
earlier, showing not much has been done since then. (9/18/09)
In mid-June the decking needed
more attention, the future ramps and I-74 roadway had received at
least one coat of asphalt around the I-85 interchange (6/14/09).
A view from 2 months earlier, showing the progress
on constructing the flyover ramp from I-74 East, the bridge
decking was in place awaiting cement pouring. (4/5/09)
Here's another view of what
was in place on the bridge pier in April, part of the flyover ramp
from I-74 East. (4/5/09)
View of the same bridge structure
about five months earlier, not much progress here, though
the bridge piers in the background have been constructed and
are near completion. (11/23/08)
A completed bridge pier can be seen in the distance,
from the now split Checker Road, now, since disconnected, renamed
Modlin Grove Road, due to I-74 construction as of early 2008. (2/23/08)
A look further to
the east shows a contractor truck (in yellow) using the I-85 North off-ramp
from I-74 which is paved to where it merges with the ramp from the flyover
ramp. (1/14/10)
Progress in landscaping
is seen from this photo looking east of I-85 in April 2010, compare this
to the photo below from three months earlier (mother nature has helped some).
(4/11/10)
The look further
down I-74 to the East shows the extent of the guardrail placement in early
2010. Orange barrels seen below from a couple months earlier to mark construction
areas have been removed. (1/14/10)
View of
the I-74 roadbed east of the I-85 interchange showing progress,
including the placement of some guardrail along the westbound roadway
and the completed grading of this section heading toward the NC 62
bridge. (11/8/09)
The view of progress in constructing
this section is shown from looking at this photo of a similar view
from June 2009. (6/14/09)
Road grading was just starting east of I-85
and west of NC 62 back in Feb. 2008. Taken just after the split of then
Checker Road. (2/23/08)
By November 2008 the ramp to
the above roadbed had been paved, but not the roadbed itself, which
looks much like the photo below. (11/23/08)
Looking eastbound
at the clearing being done for the interchange from I-85
North, September 2007.
Here's the
view approaching the construction area on I-85 North, lanes were restricted
in the area from 3 to 2, for I-74 construction a month
earlier (September 2007).
NC
62 Bridge: This bridge was completed in July 2009
and little has changed since:
However, here are the final stages of lanscaping the bridge occuring in June
2010. (6/20/10)
The
NC 62 bridge over I-74/US 311 to the east of the I-85 interchange was
largely completed in 2009 with the decking completed by February. The
only remaining project was to cut down the approaches to the bridge
to match the existing NC 62 roadway. This, as seen below, had been
largely completed by June. The bridge was opened in July.
This now is
the view is heading eastbound on NC 62 across the new bridge. By December
overhead sign assemblies for the I-85 exit to the north could be seen
from the bridge. (7/26/09)
Here's driving over the NC 62 bridge itself, some work
remained, as seen by the orange barrels on the other side. (7/26/09)
NC 62 Bridge at left showing
what remained to be done to tie the new bridge approach to existing
roadway in June 2009. (6/14/09)
The view of the bridge heading
east as of April 2009, at that time only grading has been mostly
completed, road realignment and paving were still needed. Paving
was sone in that area in the fall of 2008, since then the paving has
extended past Tuttle Road to near Poole Road. (4/5/09)
Compare progress to the way
the bridge appeared in October 2008, only the metal bridge supports
had been placed. (10/31/08)
View now looking
the other direction on NC 62 toward the bridge in January 2010, when
construction in this area was near completion. (1/28/10)
About 5 months earlier, the orange
barrels are protecting the growing grass surface on either side
of NC 62 soon after the new bridge was open. (7/26/09)
This is the
view looking west toward the NC 62 bridge in June 2009, before
asphalt had been put down. (6/14/09)
The view of the grading and
bridge looking west in April 2009, not as much progress, the alignment
crosses a roadway here, the intersection was moved back to
accomodate the new alignment of NC 62. (4/5/09)
Here's the new NC 62 roadway
alignment to cross the new bridge in April 2009, view looking
east on NC 62. The pavement on NC 62 to the south had not changed.
(4/5/09)
View from the NC 62 Bridge looking
South/East. It appears most paving and landscaping has been completed from
here to the Tuttle Road Bridge. 6/20/10)
This view is from November
2008 showing the roadbed had received its first coat of asphalt
heading east, but it didn't go too far around the corner based on
the photos below. (11/23/08)
Here's a view
to the opposite side of the bridge showing the progress
of land clearing a couple miles east of NC 62 in the Fall of
2007. (September 2007)
The view looking
westbound (north) toward the I-85 interchange. The gantry for the future
I-85 North exit sign can be seen in the distance. (1/28/10)
Tuttle Road Bridge - This
was the first bridge completed in this segment. Started in
the spring of 2007, graded fill was placed up to the western
edge of where the completed bridge in May 2008. The bridge was
open early in August 2008. The following are photos from June, November,
and December 2009, which look similar to the view in January 2010. The
first photo is from April 2010 when the last coat of asphalt was placed
on the bridge and surrounding roadways. Similar work was done on the bridges
and approaches to the south/east:
The 'completed' Tuttle Road over I-74 in April 2010. (4/11/10)
Approaching
the bridge from the east, as you can see Tuttle Road itself
was also reconstructed at the time the bridge was built, several
homes now though have steep driveways, such as the one on the right,
just before the bridge. (6/14/09)
Here's the view of the bridge
looking eastward, they may need to put more asphalt down to make it
a smoother transition onto the bridge. (12/12/09)
Progress
since June 2009 (below) can be seen in this photo looking east/south
toward Poole Road showing the addition of the possible final asphalt
layer, at least good enough for the contractor to drive on (eventually
the wrong way), and seeding of the median and surrounding surface area,
plus guardrails added to the future westbound roadway. (12/12/09)
An earlier
view from the top of the bridge from June, the curve ahead is one
of the steepest ones on this segment. (6/14/09)
This view looks
west/north from the Tuttle Road bridge and shows additional work being
performed and more guardrails along the highway than the month before.
(12/12/09)
A similar
view from November 2009 showing progress made since June in photo
below. Note the start of the placement of guardrails and the progress
in placing the final landscaping. (11/8/09)
A similar view looking toward
NC 62 in June, note some of the road surface has recently received
several layers of asphalt. (6/14/09)
Poole
Road Bridge: The bridge was opened in May 2009. By April completion
with all bridge structures complete and metal rebar decking had
been in place. Concrete pouring was starting on the decking, NCDOT
anticipated this bridge would open in June, but it was completed
sooner. A final asphalt layer was placed on the bridge in April 2010.
This is a view I could not
take before, looking at Poole Road approaching from the west. (6/14/09)
Here's what the completed
bridge looks like heading west, as you can tell, progress was
made since the photo below. (6/14/09)
Here's the view in early
April showing the cement has been poured and the rebar in place
to pour concrete for the side of the bridge. A truck actually crossed
the bridge while I was parking to take this photo. (4/5/09)
This view of the Poole Road
before construction after the road had been cut-off last fall. (10/31/08)
Looking north from the bridge
shows the progress made in paving and landscaping the area around the creek
bridge in June 2010. (6/20/10)
The completed asphalt layer
was first placed down in early May 2010 with pavement being placed around
the completed eastbound creek bridge with final landscaping starting to proceed.
(5/9/10)
Progress in grading to
the finished creek bridge can be seen north of the Poole Road bridge a month
earlier in April. (4/11/10)
The same view in
January 2010 shows earlier progress in building the bridges and the landscaping
along the eastbound roadway. This section west of the bridge is the
only part between NC 62 and just before Cedar Square Road which had
not received at least one asphalt layer. (1/14/10)
View
looking North from the Poole Road bridge in September 2009 shows
progress on grading and paving at that time, plus the completion of
the westbound bridge over the creek. (9/18/09)
The same view from the bridge
in June. Showing the progress in completing the roadbed and the creek
bridges being built about 1/4 mile away. (6/14/09)
View showing progress in
median landscaping south of the Poole Road Bridge in May 2010, the asphalt
continues south almost to the Cedar Square Road interchange. (5/9/10)
Looking east four
months earlier in January 2010 shows progress in constructing the eastbound
roadway over the winter. Notice the highway looks less complete with
the grass turning brown in this area since the fall (photo below). (1/14/10)
The
view looking east/southbound toward Cedar Square Road in September
2009 showing the progress in grading and paving the road over the
summer. (9/18/09)
The view looking east/southbound
in June 2009 does shows the progress made over the summer in grading
and paving. (6/14/09)
The
view of the Poole Road Bridge from the new Poole Road alignment
in September 2009. Compare the size of plant growth along side
the freeway to that in the photo below. (9/18/09)
The view approaching the
bridge before it opened in April 2009. (4/5/09)
Workers using boring machines
in anticipation of construction of the new Poole Road bridge in
the Fall of 2008. (11/03/08)
View of completed water runoff
drain along the westbound I-74 lanes next to Poole Road in May 2010. (5/9/10)
A number of trucks are parked
along the westbound lanes as seen from Poole Road. Apparently asphalt trucks
waiting for another batch, the contractor had problems with getting the quantities
of asphalt needed, slowing progress in May and June. (6/20/10)
View a month earlier, looking
at progress completing the freeway running parallel to the relocated Poole
Road in May 2010, at that time only one truck was left parked over the weekend.
(5/9/10)
Looking at the future
freeway from the relocated Poole Road in April 2010. Notice not much progress is observed
when compared to the photo below from the fall of 2009. (4/11/10)
A similar
view of the future freeway in October 2009. At this time there was noticable
progress in grading and placing asphalt as compared to the photo
below that was taken a year earlier. (10/12/09)
Here's what
the graded freeway looked like from the new section of Poole
Road leading to the bridge in October 2008. The road has been moved
out of the freeway alignment and built south to connect with Cedar
Square Road (the original road intersected with US 311). (10/31/08)
The Cedar
Square Road Bridge and Interchange: Bringing the freeway
by the bridge down to grade is ongoing, work was completed on the bridge
and the new alignment for the road on 11/17/2009, so traffic can
access US 311 1/2 mile south (east). The former alignment was excavated
to connect the existing roadbeds and exit ramps for the interchange on
either side.
Despite the number of trucks
parked below during May, little progress was made on the Cedar Square offramp
in the month since. (6/20/10)
It looked though that most
of the activity would occur near Cedar Square Road in May, based on the number
of construction vehicles parked near the eastbound offramp. (5/9/10)
View of Cedar Square Bridge
area progress in June 2009. (6/20/10)
A closer look on progress
in grading under the bridge, there's less grading in the right lane, but
this part of the freeway will not be needed until the section to US 220 opens
in 2012. (5/9/10)
A month earlier the piles of dirt in front of the bridge
are all that is left of the former alignment of Cedar Square Road. Work
continued to bring the freeway down to grade so that the asphalt in the foreground
can continue under the bridge. (4/11/10)
View heading across the Cedar Square Road Bridge in
December 2009, the bridge is 3 lanes wide to accomodate a left turn
lane for the I-74 East onramp on the other side. (12/12/09)
Progress on building the
eastbound offramp in April 2010. Work to complete the ramp has to wait until
all the dirt from the former alignment of Cedar Square Road can be removed.
(4/11/10)
View
under the open Cedar Square Road bridge showing the progress in grading
the future freeway, only the westbound lanes need to be completed at this
time. In March paving started on the other side of the bridge and further
east/south toward Spencer Road (1/14/10)
The view of the bridge and roadway progress
in early November 2009, 9 days before it opened. (11/8/09)
The bridge as it appeared in
October 2009. Final work was being done on the bridge deck and the
side walls to the bridge were almost complete on the north side.
(10/12/09)
View
a month earlier in September 2009 shows the support beams for the
bridge have been placed and work was starting on pouring concrete
for the bridge deck. (9/18/09)
Quite a difference in comparing
this photo from the one 3 months later above, at that time construction
of the center pier appeared to be complete, but there were no signs
of bridge decking materials in the area as of yet. (6/14/09)
Here's what the bridge pier
construction looked like with what would be the new alignment of
Cedar Square Road in April 2009. (4/5/09).
View of end of graded
roadway in December 2009. The now old alignment of Cedar Square Rd. needed
removal before grading (and paving) could continue. (12/12/09)
View of Cedar Square Interchange from new alignment of Poole Road, curving
left to meet old Cedar Square Road to intersect new alignment (4/11/10)
View looking across
the old alignment of Cedar Square Road a month earlier along what will
be the eastbound roadway, before work started on removing the old roadway
(The Poole Road connection had not been completed at this time). (3/10/10)
View looking from what
remains of the old Cedar Square alignment looking back toward Poole
Road in January 2010. Progress had been made extending asphalt
to the eastbound interchange ramp, but most of the former Cedar Square
road embankment still needed to be removed before more progress to the
east could continue. Poole Road now is extended over the old Cedar Square
alignment back to the east side of the bridge. (1/14/10)
View of the completed
section of the eastbound onramp a month earlier with final grading to
start after the old Cedar Square Road is removed (12/12/09)
Looking
back toward the Poole Road Bridge in November 2009, progress had
been made in excavating the eastbound off-ramp and placing asphalt
on the future westbound roadway. (11/8/09)
Progress
in building the eastbound offramp in November 2009 from Poole Road.
(11/8/09)
A close
look on progress in constructing the eastbound off-ramp to Cedar Square
Road (the temporary end to I-74) a month earlier in October 2009.
(10/12/09)
The
beginning of work on the eastbound offramp can be seen in this
photo from September 2009. The high ground with the barrels behind
is the current Cedar Square Road which will be removed once the new
bridge is completed. (9/18/09)
The view of the
opened new alignment of Cedar Square Road heading west toward the bridge,
the old road to the right will become an extension of Poole Road. (12/12/09)
Photo from
a month earlier showing the connection between the existing and new
alignment of Cedar Square Road almost complete. (11/8/09)
Work on
preparing the connection to the new bridge from the existing Cedar
Square Road going on in October 2009. The south side wall of the bridge
still needed to have concrete poured, but the road was close to completion.
(10/12/09)
View in early March
showing progress in removing old alignment of Cedar Square Road. Removing
rest is complicated by need to move existing intersection of Poole Road
to the east. This was completed later in March and the remaining westbound
lanes graded. (3/10/10)
View of
progress in excavating the freeway bed up to Cedar Square Road, the
dirt ramp on the right allows construction trucks to stay in the
construction area and simply cross the current Cedar Square Road when
necessary (necessitating the workers with stop signs seen above (close
to the convenient porta-potty). (10/12/09)
Another
view from October showing the extent of construction on the west
side of the freeway bed, and the other worker with the stop sign for
eastbound traffic. (10/12/09)
The view in
April 2009 from Poole Road to the current Cedar Square Road
at the start of construction beyond for the new bridge. (4/5/09)
A closer look at the westbound
onramp. This and the eastbound offramp are the only ramps that need to be
completed for the interchange to be opened. (5/9/10)
View from the Cedar Square Bridge
looking toward the end of the first part of the contract at Spencer Road.
(6/20/10)
View of progress in creating
the westbound offramp and grading the future 2012 onramp across for the end
of Poole Road. (5/9/10)
View across Cedar Square
at I-74 interchange ramps a month earlier, not much progress from January,
as seen in the photo below. (4/11/10)
The same view in
January. The intersection will be controlled by traffic signals when the
westbound onramp is open.
Both the future
on and offramps from the westbound freeway will intersect on the south
side of Cedar Square Road. This photo is of progress where the ramps
meet at the intersection in December 2009. (12/12/09)
Photo showing the
progress of connecting the off and onramps to the westbound freeway in
December 2009. (12/12/09)
The Temporary
Routing of US 311 along Cedar Square Road:
The view of the road from
the future freeway to current US 311, with final paving done in early April
2010. (4/11/10)
Until the I-74
freeway is complete to US 220, all traffic to and from the freeway
will use the new Cedar Square Road alignment seen above in December
2009 to connect to the existing US 311. Note the large concrete median,
meant to prevent easy U-turns along this stretch? (12/12/09)
In November
2009 the new alignment south of the Cedar Square bridge was complete
and traffic signals had been put up and placed on yellow flash mode
in preparation for the opening of the intersection. US 311 will be routed from the freeway
to meet its current alignment at this point. The old alignment
was to be designated US 311 Business according to plans, but NCDOT
successfully petitioned AASHTO to remove that designation along US
311's old route on Main Street through High Point from Business 85.
New signage put up on I-85 in March 2010 indicates it will not be signed
here either. (13)(11/8/09)
The same view
from just south of the current Cedar Square Road intersection
two months before, the new intersection is where the car and building
are in the center of the photo. (9/18/09)
This was
the view of the end of the new Cedar Square Road at US 311 in October
which will temporarily take I-74 traffic to and from US 311 when
the freeway first opens. In November the road appeared complete with
the exception of line striping. Notice the future signal poles on the
right and electronic loops for the signals have already been placed
under the asphalt on the bottom right. (10/12/09)
The end of the US 311 construction
zone, The next traffic light is for Spencer Road, the end point
for the first part of the project. (9/18/09)
Here's
the view approaching the construction zone from the opposite direction
on US 311 North. (10/12/09)
The
End of Phase 1 of the Construction Project:
Construction equipment as
seen from Spencer Road, the official end to the first phase of the project.
(5/9/10)
An earlier look at the end
of the first phase of the project just north of Spencer Road in
September 2009. (9/18/09)
Photos
of Work on the Last Phase, from Spencer Road to US 220:
More signs of work could
be seen in November 2009 for the next segment to be constructed
from Spencer Road to US 220 along US 311. But there were some signs work
was starting:
This road work ahead sign had appeared
along US 311 on the way through Sophia in September. (9/18/09)
Progress in clearing around
the future Sophia interchange in May 2010, looking from southbound US 311 (5/9/10)
Progress in clearing around
the future Sophia interchange in May 2010, notice new lanes being put in
for the future alignment of currrent 311. (5/9/10)
This intersection
of US 311 and Wall Brothers Road will be the location of the future
offramp from I-74 East. Wall Brothers Road will be relocated 1/4
to the west (north) and tie into what is now US 311 there. (11/8/09)
Progress in grading
the area around the interchange in March 2010. (3/10/10)
The start
of excavation can be seen back in November behind what was the pipeline
relocation construction seen a month before. (11/8/09)
This
was the appearance of grading of earth to move a pipeline in September.
This is approximately where the new freeway will cross existing
US 311. (9/18/09)
A look
at the construction at the future interchange site from the opposite
direction in October. An e-mail from a resident and a check of the
plans confirmed they are moving the utilities in order to construct
the interchange with existing US 311. (10/12/09)
A view
at the end of the construction zone along North US 311 in Sophia.
(10/12/09)
Construction
of the US 220 Interchange
There is
more evidence of construction on this part of the project. In August
2009 jersey barriers went up and construction equipment appeared along
US 220 between the current US 311 exit and the Pineview Street exit.
Road construction
signs can be seen from the onramp from US 311 to US 220 South (Future
I-73/74). (9/18/09)
The
signs indicate the placement of barriers along the right shoulder
(there on the left too, but not mentioned) where the ramps to and
from I-74 will be built. (9/18/09)
Approaching the interchange
construction area in May 2009, showing progress on building the two interchange
bridges and ramps. (5/9/10)
View approaching the construction
zone a month earlier, note progress on the right side bridges compared to
that in the photo below. (4/11/10)
Closeup view of the west side
of the second bridge for the ramp to I-73 (US 220) North in May 2010, note
the grading behind the bridge support structure. (5/9/10)
A close look a month earlier
at the I-74 West Flyover ramp, this ramp will go both over US 220 and the
bridge carrying traffic to I-73 north (4/11/10)
A closer look at the second
ramp going southbound, notice this is lower and made of concrete blocks,
as opposed to the metal work in the previous bridge support (4/11/10)
View of the construction site
approaching on US 220 North in May 2010. (5/9/10)
Closeup of the two bridge
piers and progress on the northbound side of US 220 building the future
interchange ramps in May 2010. (5/9/10)
The progress on the two
piers for the flyover ramps in March, the crane is completing work on the
second pier. (3/10/10)
Progress in building up the
grade for the I-74 East flyover ramp looking from US 220 Southbound in May
2010. (5/9/10)
The first piers
for the flyover bridges and the initial phases of land clearing for
the I-74 to I-73 north onramps can be seen across the southbound US 220
lanes. (11/8/09)
The cranes
in the background used to help start construction of the piers for
the flyover ramps in November 2009 as seen from North US 220. (11/8/09)
Closer
view northbound in October of construction equipment in the median
before the start of construction of the 2 flyover ramps that will cross
US 220 (I-73) (10/12/09)
View of progress in interchange
area as of April 2010, with the center supports for the two I-74 ramps in
the distance. (4/11/10)
The view of construction
progress on the flyover ramps and interchange clearing in March 2010.
(3/10/10)
View northbound
showing progress in clearing the construction zone a few months earlier
in November 2009. (11/8/09)
Here
is the construction area in September 2009 heading southbound
with barriers on the shoulders surrounding the construction equipment
that was then present. (9/18/09)
View of progress on Westbound
I-74 ramp to flyover bridge from southbound US 220 in April 2010. (4/11/10)
View of progress a month
earlier in March in creating northbound ramp to flyover bridge heasing
northbound. (3/10/10)
Six
months earlier you could see the start of the removal of trees across the
road along the northbound roadway. Land needed to be cleared for
the I-74 West onramp and the flyover ramp to US 220 (I-73) North.
(9/18/09)
Progress
in tree removal in September 2009 and construction equipment can
be seen better looking across toward the northbound lanes of the
highway. (9/18/09)
View going
northbound in October showing progress in building what will be
the flyover ramp taking I-74 West to High Point, this is same area
seen in photo above in September. (10/12/09)
View in
October on new construction area which will be for the offramp from
I-74 East to I-73 North (10/12/09)
The
construction zone ends southbound just before the Pineview Street
bridge, the zone is about two miles in size. (9/18/09)
Comment: After this section
of freeway is built to replace US 311, decommission
this intrastate US route which doesn't meet current
AASHTO U.S. Route guidelines (at least 200 miles long, in
more than 1 state). The section north of I-40 (not along
I-74's route) could be NC 311. NCDOT has already decided to decommission
the old route and not call it Business US 311.
Here's a map from the Greensboro
News & Record showing the new sections of I-74
under construction:
Sources: NC Transportation Map 2001.
(1) Hall, Tony. 1997. "I-74 Coming to a Town Where
It's Not Welcome." News & Record (Greensboro,
NC). Sept. 27: B1.
(2) Muschick,
Paul. 1999. "Route for 311 Bypass to be Unveiled in
Randleman." News & Record (Greensboro, NC).
August 9.
(3) NCDOT. June 2008. State Transportation Improvement
Program, 2009-2015, Division 8, p. 8-27.
(4) NCDOT. 2007. Construction
Progress Report, Contract C201715, Downloaded June
15, 2009.
(5) NCDOT. 2006. Contract Documents,
NCDOT Signing Section, Contract C201296, Project R-0609-A.
Downloaded from link at: http://dotw-xfer01.dot.
state.nc.us/dsplan/2007%20Highway%20Lettings/4-17-2007/ on 2/23/07.
(6) NCDOT. 2008. "Transportation
Board Awards More than $265 Million in Highway Contracts
for 29 Counties." Press Release. NCDOT Communications Division,
8/7/08.
(7) Kimbrough, Pat. 2003. "Randolph Leaders Lobby
State for I-74." High Point (NC) Enterprise.
Dec. 1.
(8) NCDOT.
2007. Program Development Branch. "12 Month Tentative
Letting List for April 17, 2007" (Typically construction
projects are approved and/or start a month after the project
is let, this project is to start the last week in May).
(9) Dominello,
Amy. 2005. "U.S. 311 Bypass Work Delayed."
News & Record (Greensboro, NC). May
2, downloaded from http://blog.news-record.com/staff/fastforward/archives/2005/05/from_sundays_pa.html,
Oct. 1.
(10) NCDOT. Sept. 2004. R-2606 Project
Breakdown Map.
(11) Information
from e-mails from Bill Travers 3/6/08, 5/23/08, 8/11/08,
10/20/08, 2/7/09, 8/5/09, 3/14/09.
(12) Information from e-mail from Ronald
Shaw 3/6/09.
(13) AASHTO. 2009. Applications to Standing Committee
on Highways, Special Committee on U.S. Route Numbering, October
1. NC Petition Regarding US 311 Business in Guilford County. Downloaded
from: http://cms.transportation.org/sites/route/docs/NC%20Elim%20US%20311%20Bus%20Guilford%20Aug%
2009.pdf 10/2/09.
US 311 shield courtesy of David R. Kendrick's Shield's
Up!